Someone points to a blast plan and says, “That’s the burden.” Another person points to the same drawing and calls it spacing. Both are looking at a distance, but they’re talking about different parts of the design. Add a second drawing revision or a different floor reference, and a simple conversation can get confusing fast.
Burden, spacing, stemming and subdrill are four of the first terms you’ll hear in open-cut drill and blast. This guide explains what each one describes, where to look for it on a drawing, and why the same words can be misunderstood in a design review. The examples are illustrative; they show how to read the records and ask better questions.
Start with the two views of the drawing
A plan view looks down on the bench. It shows the rows of holes, their positions and the surrounding features. A cross-section is a vertical slice through the bench. It shows the relationship between the surface, the holes and the intended working floor. Some sections exaggerate the vertical scale, so I read the dimensions and legend instead of judging distances by eye.
Keep one distinction in mind as you switch between views: burden and spacing describe relationships across the bench; stemming and subdrill describe parts of a hole in relation to the collar or the floor. A plan view and a cross-section answer different questions about the same work.
1. Burden: identify the face or row being referenced
Burden describes the distance between a blast hole and the relevant free face, or the distance between rows where the drawing uses that convention. A free face is an exposed rock surface. The word “relevant” matters: the label is only meaningful if you know which face or row the author used as the reference.
A review example: A marked-up drawing refers to “the face”, but it shows both a survey line and a proposed excavation outline. Before discussing the annotation, I’d ask which line the author meant and which survey revision it came from. That turns an ambiguous markup into something another engineer can verify.
2. Spacing: follow the row
Spacing describes the distance between neighbouring holes in the same row. It’s easiest to identify on the plan view once you’ve worked out which holes are grouped together. Burden and spacing can both appear as dimension lines on one drawing. Read the endpoints before deciding which term applies.
A review example: On a staggered layout, the closest-looking dot may belong to the next row. If a markup just says “spacing looks different here”, someone reading it later may pick a different pair of holes. Referencing the row or hole IDs gives the reviewer a clear starting point.
3. Stemming: read the label near the collar
Stemming is inert material represented in the upper part of the hole, near the collar, where the hole opens at the surface. The term can refer to the material itself or to the section shown in a drawing or field record. The legend and column heading tell you which meaning applies.
A review example: A summary says “stemming recorded”, but the linked document is a design drawing. The drawing shows what was intended. To understand what was recorded in the field, I’d look for the corresponding field record and check that it refers to the same hole and revision. If that record isn’t available, I’d keep the distinction visible.
4. Subdrill: find the planned floor first
Subdrill is the part of a hole that extends below the planned bench floor. Total hole depth describes the full length of the hole from the collar. Subdrill describes only the part beyond the floor reference. A cross-section makes the difference easier to see because it shows where the planned floor sits in relation to the hole.
A review example: A post-work survey shows an uneven floor, and the report includes a note about subdrill. I’d first identify whether the note refers to the design floor or the surveyed surface. The two records can be useful together, but they represent different things: one is a design reference and the other is an observation.
What I check before a peer review
Good reviews often start by making sure everyone is discussing the same drawing and the same evidence. These are the questions I’d want answered before relying on a markup, handover or post-blast report:
- Are we looking at the same revision? Check the drawing identifier, revision and linked survey so comments carry the right context.
- What are the reference points? Identify the face, row, collar or planned floor being discussed. If a comment says only “here”, make it specific enough for the next person to find.
- Is this planned, recorded or observed? Keep design intent separate from field records and post-work observations. If a record is missing, call it out.
- What evidence supports the conclusion? A photo, a survey surface and a vibration record answer different questions. Record what each one shows and flag what still needs review.
Don’t let one observation explain the whole result
After the work, different teams may notice different things. Production might comment on how the broken rock handled, survey might document the floor surface, and the monitoring team might report a vibration reading. Those observations belong together in the review, but none gives a complete picture on its own. Keep the observation, its source and any interpretation distinguishable in the report.
For example, a photo of coarse rock can tell you what was visible at one place and time. It can’t establish why the rock broke that way across the whole bench. A better note identifies where and when the photo was taken and leaves the cause open for the responsible team to assess alongside the other records.
Frequently asked questions
What’s the difference between burden and spacing?
Burden refers to the relationship to a face or another row. Spacing refers to neighbouring holes along the same row. If you’re unsure which dimension you’re looking at, check where the line starts and ends.
Is subdrill the same as total hole depth?
No. Total depth refers to the entire hole; subdrill refers to the part below the planned bench floor.
Can a blast plan tell me what a vibration monitor recorded?
No. The plan shows design intent. For a measured result, use the monitoring report and confirm which event and monitoring point it refers to. See my Oaklands Junction Quarry case study for an example of that review, or Resources Victoria’s guidance on ground vibration and airblast for the regulatory context.
The habit I’d pass on to a graduate engineer: whenever one of these terms comes up in a review, point to its reference on the drawing and say which record you’re using. That gives the next person enough context to check your reasoning without having to reconstruct the conversation.